Define the following: Average demand, Maximum demand, Demand factor, Load factor.
Average Demand : the Average power requirement during some specified period of time of considerable duration is called the Average Demand of installation.
maximum Demand : the maximum Demand of an installation is defined As the greatest of All the Demand, which have occurred during a given period. It is measured accordingly to specifications, over a prescribed time interval during a certain period.
Demand Factor : It is defined As the ratio of actual maximum Demand made by the load to the rating of the connected load.
load Factor : It is defined As the ratio of the Average power to the maximum demand.
maximum Demand : the maximum Demand of an installation is defined As the greatest of All the Demand, which have occurred during a given period. It is measured accordingly to specifications, over a prescribed time interval during a certain period.
Demand Factor : It is defined As the ratio of actual maximum Demand made by the load to the rating of the connected load.
load Factor : It is defined As the ratio of the Average power to the maximum demand.